Content provided by OSSA LNG. All podcast content including episodes, graphics, and podcast descriptions are uploaded and provided directly by OSSA LNG or their podcast platform partner. If you believe someone is using your copyrighted work without your permission, you can follow the process outlined here https://staging.podcastplayer.com/legal.

This week, we pull back the curtain on the critical, steam-heated heat exchangers located in the cargo machinery room: the High Duty (HD) Gas Heaters and the related Boil-Off/Warm-Up Heaters. Manufactured by specialized firms like DongHwa Entec or Cryostar, these Shell and U tube devices are essential for safe and efficient LNG Carrier Operations.

Why These Heaters Are Critical

These units perform several high-stakes jobs:

1. Cargo Tank Warm-Up: Before dry docking or internal inspection, tanks must be heated. The HD Gas Heaters warm massive volumes of LNG vapor (or inert gas from the IGG) delivered by the HD compressor, often requiring both sets of heaters to run simultaneously. The system strictly controls the temperature, ensuring the outlet does not exceed +80°C to prevent damage to cargo piping insulation and safety valves.

2. Fuel Supply: They prepare gas for combustion, heating Boil-Off Gas (BOG) for the Gas Combustion Unit (GCU), or supplying vapor for the Dual Fuel Generator Engines (DFGEs) via dedicated Fuel Gas Heaters. For BOG supply, the outlet temperature is carefully regulated, often between 30°C and 70°C.

Precision Engineering & Control

The temperature output is governed by sophisticated Split Range Control logic. A single controller manages two pneumatic valves simultaneously: one on the heater inlet line and one on the bypass line. When starting up for warm-up mode, the bypass valve is initially fully open, allowing cold vapor to bypass the heating element, while the inlet valve is fully shut. The Integrated Automation System (IAS) then makes continuous, precise, and inverse adjustments to maintain the set point.

Safety Protocols: Preventing the Deep Freeze

Tune in to learn why preheating the heater with steam is mandatory. The steam supply must be started before any cold vapor flow is permitted through the system. This precaution prevents the formation of ice and possible damage to the heater tubes. We also discuss the crucial safety interlocks: the unit automatically trips and the controller output is forced to 0% upon detecting serious conditions, such as High-High Condensate Level (LSHH) or dangerously High-High Outlet Temperature (TSHH).

Don't miss this in-depth look at the complex machinery keeping Cryogenic Technology safely managed at sea!

SEO Keywords: LNG Carrier Operations, HD Gas Heater, Cryogenic Technology, Boil-Off Gas (BOG), Split Range Control, LNG Tank Warming, Maritime Engineering.

--------------------------------------------------------------------------------